Planning Strategy 60 Planning with Planning Material
For optimal viewing of the slides, please press Ctrl + Shift + F
✅ Planning Strategy 60 — Planning with Planning Material
📌 Where It’s Used:
SAP PP (Production Planning) module — typically for configurable or variant-rich products.
📂 What Is It?
Planning Strategy 60 = Planning with Planning Material.
You plan a “planning material” instead of directly planning the end product.
✔️ Useful when you have a generic product (planning material) that covers multiple variant products.
🎯 Key Objective:
✅ Simplify planning for configurable or multi-variant products.
✅ Reduce master data maintenance for each variant.
✅ Allow MRP to plan in bulk at the generic level, then link real customer orders to the variants.
🗂️ How It Works:
✅ 1️⃣ Planning Material Master Setup
- Create a Planning Material (e.g., generic bike frame).
- Assign Strategy 60 in MRP 3 View.
- Link Planned Product (finished product) to Planning Material via Material Master → MRP 3 View → Planning Material field.
✅ 2️⃣ PIR Creation
- Create Planned Independent Requirements (PIRs) for the Planning Material — not for each variant.
- Tcode: MD61.
✅ 3️⃣ Sales Order Creation
- Customer orders actual configured variant (e.g., red mountain bike).
- System links Sales Order to the Planning Material’s PIRs — consumes planned stock.
✅ 4️⃣ MRP Run
- MRP plans based on the Planning Material.
- Planned Orders created for the Planning Material.
- When converting to production orders, you manufacture the variant.
🔗 Example Scenario:
- Planning Material: Generic Bike Frame (FG100)
- Variants: Red Bike (FG100-R), Blue Bike (FG100-B)
- PIR created for FG100.
- Customer orders FG100-R.
- System reduces PIR for FG100 by the Sales Order quantity for FG100-R.
✔️ This avoids separate PIRs for each variant!
📊 Key Tcodes:
TcodePurposeMD61Maintain PIRs for Planning MaterialMD04Stock/Requirements List — see link between Planning Material and variant Sales OrdersVA01Create Sales Order for variantMD02Run MRP for Planning Material
📂 Key Tables:
TableDescriptionPBIMIndependent Requirements for Planning MaterialVBAPSales Order Items — links variant to Planning MaterialMDVMMRP Lists
✅ Best Use Case:
- Mass-customized products with many variants.
- When base components are the same, but final configuration varies.
- Automotive, electronics, bikes, furniture.
✅ Conclusion:
🔑 Strategy 60 — Planning with Planning Material lets you:
✔️ Plan efficiently at the generic level.
✔️ Cover real customer-specific variants.
✔️ Optimize master data and planning effort.
It’s a smart way to balance forecast-based MTS and real customer orders in MTO, especially for variant-heavy industries!