Quiz Explanation

1. What is the purpose of collective orders?  

A. To manage production orders for an entire finished product on multiple levels 

B. To post production costs on a cost collector instead of the production order 

C. To combine order management of co-products and by-products with the main product 

D. To post any component withdrawals single back flush with order confirmation 

Answer: A  

2. Your production planners must execute planning only for specific resources. How can you achieve this in  Advanced Planning (PP"/OS)?  

A. Use a heuristic.  

B. Use a propagation range.  

C. Use a planning group.  

D. Use a resource group 

Answer: A  

3. For what production type are production orders used?  

A. Replenishment controlled by control cycles  

B. Process manufacturing processes  

C. Period and quantity-oriented production 

D. Discrete manufacturing processes  

Answer: D  

4. An issue storage location was NOT found through the work center,bill of material (BOM)item, or material  master. What determines whether the storage location can be derived from the production version?  

a. Plant Data  

b. MRP Group  

c. MRP Profile  

d. MRP Controller  

Answer: B  

5. Where does the system check master data selection sett ngs during the creation of planned orders and  production orders? Note:There are 3 correct answers to this question.  

a. In the routing  

b. In the MRP controller  

c. In the production version 

d. In the production order type 

e. In the bill of materials (BOM) 


Answer: ABD 

6. How can you carry out cost object controlling for production orders? Note:There are 2 correct answers to  this question. 

A. Order-related  

B. Cost-related  

C. Product-related  

D. Milestone-related  

Answer: AC  

7. What determines whether the planned independent requirements in MRP consume other requirements? 

A. Requirements type  

B. Requirements profile  

C. Consumption sequence procedure  

D. Order type  

Answer: A  

8. Which of the following elements does MRP take into account during net requirement calculation? Note:  There are 2 correct answers to this question.  

A. Safety stock  

B. Purchase orders  

C. Lot size  

D. Maximum stock level  

Answer: AC  

9. Why would you use phantom assemblies? Note: There are 3 correct answers to this question. 

A. To make the assignment of components easier  

B. To reduce the number of material masters  

C. To simplify the structure of bills of material  

D. To increase the number of planning levels  

E. To reduce the number of changes required in bills of material  

Answer: ACE 

10. What is a work center hierarchy in SAP S/4HANA capacity planning?  

A. A group of alternative work centers for production, structured in hierarchy levels by prior ties 

B. A group of alternative work centers providing a cumulative available capacity for production 

C. A group of work centers in a parallel sequence that is used to split product on quantities and work on  them in parallel 

D. A group of work centers in a production line being used in sequence for production 

Answer: B  



Complete and Continue