Planning Strategy 60 Planning with Planning Material

For optimal viewing of the slides, please press Ctrl + Shift + F

Planning Strategy 60 — Planning with Planning Material


📌 Where It’s Used:

SAP PP (Production Planning) module — typically for configurable or variant-rich products.


📂 What Is It?

Planning Strategy 60 = Planning with Planning Material.
You plan a “planning material” instead of directly planning the end product.

✔️ Useful when you have a generic product (planning material) that covers multiple variant products.


🎯 Key Objective:

✅ Simplify planning for configurable or multi-variant products.
✅ Reduce master data maintenance for each variant.
✅ Allow MRP to plan in bulk at the generic level, then link real customer orders to the variants.


🗂️ How It Works:

1️⃣ Planning Material Master Setup

  • Create a Planning Material (e.g., generic bike frame).
  • Assign Strategy 60 in MRP 3 View.
  • Link Planned Product (finished product) to Planning Material via Material Master → MRP 3 View → Planning Material field.

2️⃣ PIR Creation

  • Create Planned Independent Requirements (PIRs) for the Planning Material — not for each variant.
  • Tcode: MD61.

3️⃣ Sales Order Creation

  • Customer orders actual configured variant (e.g., red mountain bike).
  • System links Sales Order to the Planning Material’s PIRs — consumes planned stock.

4️⃣ MRP Run

  • MRP plans based on the Planning Material.
  • Planned Orders created for the Planning Material.
  • When converting to production orders, you manufacture the variant.

🔗 Example Scenario:

  • Planning Material: Generic Bike Frame (FG100)
  • Variants: Red Bike (FG100-R), Blue Bike (FG100-B)
  • PIR created for FG100.
  • Customer orders FG100-R.
  • System reduces PIR for FG100 by the Sales Order quantity for FG100-R.

✔️ This avoids separate PIRs for each variant!


📊 Key Tcodes:

TcodePurposeMD61Maintain PIRs for Planning MaterialMD04Stock/Requirements List — see link between Planning Material and variant Sales OrdersVA01Create Sales Order for variantMD02Run MRP for Planning Material



📂 Key Tables:

TableDescriptionPBIMIndependent Requirements for Planning MaterialVBAPSales Order Items — links variant to Planning MaterialMDVMMRP Lists



Best Use Case:

  • Mass-customized products with many variants.
  • When base components are the same, but final configuration varies.
  • Automotive, electronics, bikes, furniture.

Conclusion:

🔑 Strategy 60 — Planning with Planning Material lets you:
✔️ Plan efficiently at the generic level.
✔️ Cover real customer-specific variants.
✔️ Optimize master data and planning effort.

It’s a smart way to balance forecast-based MTS and real customer orders in MTO, especially for variant-heavy industries!