Set advanced planning for material master for APO PPDS in S/4

📌 Set Advanced Planning for Material Master (APO PP/DS) in S/4HANA

To use PP/DS (Advanced Planning) in S/4HANA, the material must be enabled for advanced planning in the Material Master.

🔹 Steps

1️⃣ Open Material Master
Transaction: MM02

2️⃣ Go to Advanced Planning View

3️⃣ Activate the field:
Advanced Planning = Active

4️⃣ Maintain required planning parameters such as:

  • PP/DS Planning Procedure
  • Heuristic
  • Planning Horizon

5️⃣ Ensure required master data exists:

  • BOM
  • Routing
  • Production Version
  • Work Center / Resource

6️⃣ Create PDS (Production Data Structure)
Transaction: /SAPAPO/CURTO_CREATE

7️⃣ Run planning and check results using:

  • /SAPAPO/RRP3 – Product View
  • /SAPAPO/CDPS0 – Planning Board

💡 Conclusion

Activating Advanced Planning in the material master enables the material for PP/DS detailed planning and scheduling in S/4HANA.